Construction Process

At Homebuyers Centre, we’ve been proudly helping first home buyers achieve their home ownership dream for over 19 years. The knowledge and commitment to quality we have gained over this time has enabled us to stream line the building process, resulting in a hassle free and enjoyable building experience for you.

Whether you choose your own new home design, or a house and land package, our dedicated and professional team have proven time and time again that by using only the best products and materials on the market and constructing homes in an average of 24 weeks, we are the market leaders in both quality and service.

The table below explains what happens at every stage of the building process during pre-construction and construction

*Construction times may vary in the South West

Pre-Construction Construction
Preliminary works Contracts
Finance Interview
Title
Information
Finance application
Building License Application
Pre-start interview
Final amendment of plans
Finance approval
Building licence approval
Water Corporation approval
Land settlement
Approximately 20 - 24 Weeks
Commence Construction
Earthworks
Concrete Footings and Slab
Curing of floor slab
Delivery of bricks and window
Bricklaying
Delivery of roof timber
Roof carpentry
Gutters and down pipes
Electrical wiring and plumbing tube
Roof Cover
Plaster float (internal grey render)
Ceilings and cornices
Plaster set (internal white plaster)
Lock up external doors and windows
Fitting of doors and cabinets
installation of bath and toilets
Ceramic wall and floor tiling
Painting
Electrical completion
Plumbing completion
Site clean and internal clean
External clean
External paving
Floor coverings
Window treatments
Pre-handover inspection
Completion of pre-handover items
Handover and key collection
Approximately 24 Weeks
Approximately 44-48 Weeks Total